36men can do a work in 25 days .So how many day can 30 men can do it

Answers

Answered by djsingh50007
1

Answer:

30 men can do the work in 30 days

Explanation:

  • 36 men can do a work in 25 days
  • then 1 man can do that work in 36×25 days
  • so,30 men can do the work in 36×25 days

30

  • =6×25 days

5

  • =6×5 days

1

so,6×5=30 days