37) 27 worksmen are employed to finish a certain work in 42 days but it found that in 21 days
only 1/5 work is done. How many more men must be taken to finish the work in time?
D) 108 men
A 27 men
C) 81 men
B) 54 men.β
Answers
Answered by
1
Answer:
more 27
Step-by-step explanation:
because 27 men in half completed 1/5 work
Answered by
3
There are 81 more men needed to finish the work in time. and Option 'c' is correct.
Step-by-step explanation:
Since we have given that
Number of worksmen = 37
Number of days = 42
In 21 days, only work is done.
Remaining work =
So, we will use "time and work":
According to question, it becomes,
So, Number of more men is given by
108 - 27 = 81
Hence, there are 81 more men needed to finish the work in time. and Option 'c' is correct.
# learn more:
6. 40 men are employed to finish a work in 48 days. but it is found that in 24 days only 1/4 work is done. how many more men are required in order to finish the work in time? (a) 24 men (b) 16 men (c) 22 men (d) 20 men
https://brainly.in/question/5871321
Similar questions