Math, asked by sirichandana73, 1 year ago

37) 27 worksmen are employed to finish a certain work in 42 days but it found that in 21 days
only 1/5 work is done. How many more men must be taken to finish the work in time?
D) 108 men
A 27 men
C) 81 men
B) 54 men.​

Answers

Answered by hardijain
1

Answer:

more 27

Step-by-step explanation:

because 27 men in half completed 1/5 work

Answered by windyyork
3

There are 81 more men needed to finish the work in time. and Option 'c' is correct.

Step-by-step explanation:

Since we have given that

Number of worksmen = 37

Number of days = 42

In 21 days, only \dfrac{1}{5} work is done.

Remaining work = 1-\dfrac{1}{5}=\dfrac{5-1}{5}=\dfrac{4}{5}

So, we will use "time and work":

According to question, it becomes,

\dfrac{27\times 21}{\dfrac{1}{5}}=\dfrac{x\times 21}{\dfrac{4}{5}}\\\\27\times 4=x\\\\x=108

So, Number of more men is given by

108 - 27 = 81

Hence, there are 81 more men needed to finish the work in time. and Option 'c' is correct.

# learn more:

6. 40 men are employed to finish a work in 48 days. but it is found that in 24 days only 1/4 work is done. how many more men are required in order to finish the work in time? (a) 24 men (b) 16 men (c) 22 men (d) 20 men

https://brainly.in/question/5871321

Similar questions