Math, asked by mayurvijaypatil26420, 7 months ago

37. A can do a piece of work in 30 days while B alone can do it in 40 days. In how
many days can A and B working together do it? (1) 16 (1/7) (2) 17 (1/7) (3) 18 (1/7)
(4) 19 (117)​

Answers

Answered by IndianChamp
1

work and work...xd

Step-by-step explanation:

assume they r doing same amount of work but difference is only efficiency

so let's assume they r doing 120 units of work

so A can do 120 units of work in 4 days (120/30)

and B cand do 120 units of work in 3 days.

so together they can do same work in 120/3+4

which is 17(1/7) that means option B

Answered by TheVenomGirl
36

Answer :

  • A and B together can complete the work within \sf \: 17 \dfrac{1}{7}  \: days . [Option 2]

Explanation :

We are given that A can do a piece of work within 30 days, while B can do the same work in 40 day's.

So,

Total work completed by A within a day = 1/30

Total work completed by B within a day = 1/40

Together work done by A and B within a day :

⇛ A + B

⇛ 1/30 + 1/40

⇛40 + 30 /1200

⇛ 70/1200

⇛ 7/20

Total no. of days required for A and B to finish the work together :

\sf \dfrac{1}{7/120}

\sf \: 17 \dfrac{1}{7}  \: days

Therefore, A and B together can complete the work within \sf \: 17 \dfrac{1}{7}  \: days .

━━━━━━━━━━━━

★ Alternative Method :

We can calculate this by an alternative method too! [By LCM]

LCM of 30 & 40 is 120

  • 120/30 = 4 [ A ]

  • 120/40 = 3 [ B ]

Hence,

Total work done together :

⇛ 120/7

⇛ 17.15

\sf \: 17 \dfrac{1}{7}  \: days

Therefore, A and B together can complete the work within \sf \: 17 \dfrac{1}{7}  \: days .

━━━━━━━━━━━━

Similar questions