37. A can do a piece of work in 30 days while B alone can do it in 40 days. In how
many days can A and B working together do it? (1) 16 (1/7) (2) 17 (1/7) (3) 18 (1/7)
(4) 19 (117)
Answers
work and work...xd
Step-by-step explanation:
assume they r doing same amount of work but difference is only efficiency
so let's assume they r doing 120 units of work
so A can do 120 units of work in 4 days (120/30)
and B cand do 120 units of work in 3 days.
so together they can do same work in 120/3+4
which is 17(1/7) that means option B
Answer :
- A and B together can complete the work within . [Option 2]
Explanation :
We are given that A can do a piece of work within 30 days, while B can do the same work in 40 day's.
So,
Total work completed by A within a day = 1/30
Total work completed by B within a day = 1/40
★ Together work done by A and B within a day :
⇛ A + B
⇛ 1/30 + 1/40
⇛40 + 30 /1200
⇛ 70/1200
⇛ 7/20
★ Total no. of days required for A and B to finish the work together :
➟
➟
Therefore, A and B together can complete the work within .
━━━━━━━━━━━━
★ Alternative Method :
We can calculate this by an alternative method too! [By LCM]
LCM of 30 & 40 is 120
- 120/30 = 4 [ A ]
- 120/40 = 3 [ B ]
Hence,
★ Total work done together :
⇛ 120/7
⇛ 17.15
⇛
Therefore, A and B together can complete the work within .