Math, asked by sara5225, 10 hours ago

37. If 6 men can do a piece of work in 12 days working 8 hours a day, how many men are require complete the same work in the same number of days working 6 hours a day?

Answers

Answered by HB987
1

Answer:

Step-by-step explanation:

Work done = No. of men x Days x Hours

Work done by 6 men = 6 x 12 x 8

Let the required no. of men be y

Now , Work done by y no. of men =  y  x 12 x 6

Since the same amount of work is required to be done,

 6 x 12 x 8  =  y  x 12 x 6

y = 6 x 12 x 8

     12 x 6

y = 8

Therefore the required no. of men is 8