Math, asked by bengaltiger08, 5 months ago

385 workers can build a road in 17 days. But due to advancement of rainy season.Panchayat decided to finish the work in 11 days. How many more workers needed to do it?​

Answers

Answered by ArriyunnaBrown
1

Answer: I would say 2,310 workers.

Step-by-step explanation:

Answered by tiyasamalabika
0

Answer:

Answer= no of more men needed is 210.

Step-by-step explanation:

In 17 days a road is built by 385men.

∴ in 1 day the road is built by 385 × 17 men.

∴ in 11 days the road is built by (385 ×17)/11 men  

         = 595 men

∴ no of more men= 595-385= 210 men

Answer= no of more men needed is 210.  