385 workers can build a road in 17 days. But due to advancement of rainy season.Panchayat decided to finish the work in 11 days. How many more workers needed to do it?
Answers
Answered by
1
Answer: I would say 2,310 workers.
Step-by-step explanation:
Answered by
0
Answer:
Answer= no of more men needed is 210.
Step-by-step explanation:
In 17 days a road is built by 385men.
∴ in 1 day the road is built by 385 × 17 men.
∴ in 11 days the road is built by (385 ×17)/11 men
= 595 men
∴ no of more men= 595-385= 210 men
Answer= no of more men needed is 210.