39 men can repair a road in 12 days by working for 5hr a day how many days will 30 men can repair the road working 6hr a day
Answers
Answered by
1
Let the required number of days be x.
Less persons, More days (Indirect Proportion)
More working hours per day, Less days (Indirect Proportion)
Persons30:39Working hours/day6:5}⋮⋮ 12:xPersons30:39Working hours/day6:5⋮⋮ 12:x
=> 30 * 6 * x = 39 * 5 * 12
=> x= 13
Less persons, More days (Indirect Proportion)
More working hours per day, Less days (Indirect Proportion)
Persons30:39Working hours/day6:5}⋮⋮ 12:xPersons30:39Working hours/day6:5⋮⋮ 12:x
=> 30 * 6 * x = 39 * 5 * 12
=> x= 13