39 persons can repair a road in 12 days working 5 hours per day. In how many days will 30 persons
working 6 hours per day complete the work?

Answers

Answered by alladagouthamkrishna
1

Answer:

Step-by-step explanation:

no of days = x

30 x 6 x {x} = 39 x  5 x 12

39 x 5 x 12/ 30 x 6 x {X}

= 13 days