Math, asked by br10215040612, 2 months ago

3Men and 2 boys finished a work in 6 days.5 men and 7 boys finished the same work in 3 days.in how many days 2 men and 5 boys can complete this work.​

Answers

Answered by rutikpatil51
2

Step-by-step explanation:

3 men + 2 boys complete work in 6 days. => 6 men + 4 boys can complete in 3 days. We further know 5 men + 7 boys can complete work in 3 days. => 11 boys can complete work in 6 days.

Answered by sntechncal
1

Answer:

6 days

Step-by-step explanation:

3 men + 2 boys complete work in 6 days.

=> 6 men + 4 boys can complete in 3 days.

We further know 5 men + 7 boys can complete work in 3 days.

=> 1 man = 3 boys

=> 11 boys can complete work in 6 days.

Now 2 men and 5 boys means 11 boys.

=> They complete work in 6 days.

Similar questions