4. 12 Men or 15 women can do a piece of
work in 21 days. Find the number of days
required to complete the same work by 6
men and 10 women.
(3) 21 (4) 24
(1) 15
(2) 18
Answers
Answered by
0
I think the answer will be (2) 18
Answered by
1
Answer:
12 men take 21 days to complete a piece of work. 1 man takes (12 × 21) = 252 days.
15 women take 21 days to complete a piece of work. 1 woman takes (15 × 21) = 315 days.
In 1 day, 1 man does (1/252) of the work.
In 1 day, 1 woman does (1/315) of the work.
In 1 day, 6 men and 10 women can do 6(1/252) + 10(1/315) = (1/18) of the work.
(1/18) of the work done in 1 day.
18(1/18) of the work done in 18 days.
Step-by-step explanation:
THANKS