4. A and B can do a work in 12 and 20
days respectively. If, after they work at it
together for some time, c, who can do the
whole work in 10 days, finishes it in 2
days, how long did A and B work?
o days
Answers
Answered by
23
Answer:-
A's one day work = 120
A's 4days work = 120×4=15 part
Remaining part = 1−15=45
B's one day work = 112
(A+B)'s one day work = 120+112=860=215
45 part can be finished by A and B in
= 45×152 = 6 days
The complete work will be finished in 6+4 = 10 days.
hope it is helpful for you ✌