4) A, B and C can do a place of work in 38, 54 and 72 days
respectively. They started the work but A left 8 days before
de completion of the work while B left 12 days before the
completion. The number of days for which worked is
C1 12
924
Answers
Answered by
1
Answer:
Step-by-step explanation:
A does the work in 36 days.
∴ In 1 day A does
1/36 work.
B does the work in 54 days.
∴ In 1 day B does
1/54 work.
C does the work in 72 days.
∴ In 1 day C does
1/72 work.
Let the work is finished in x days.
So A works for x-8 days.
∴ A does
x−8 / 36 work
B works for x-12 days.
∴ B does
x−12/54 work.
C works for x days.
∴ C does
x/72 work.
The sum of their works = the whole work = 1 work.
∴ (x−8/36)+(x-12/54)+(x/72) = 1
(6x-48+4x-48=3x)/216=1
(13x-96)/216=1
13x=312
x=24
So the work is finished in 24 days.