4.A.B and C can do a work separately in 16, 32 and 48 days, respectively. They started the work together but B leaving off 8 days and C, 6 days before the completion of the work. In what time is the work finished? [SSC CGL 2015] (a) 9 days (b) 10 days (c) 14 days (d) 12 days
Answers
Answered by
12
Answer:
14 days