4.
A can build a wall in 20 days, B can build it in 25
days, C aan destroy the complete wall in 40 days.
They start work on alternate days in such a way
that, A start the work, followed by B next day,
then by C next day, then A next day and so on.
How many days will it take to complete the wall if
it's given that once the wall has been made, none
of A, B and C work on the wall?
Answers
Answered by
1
Answer:
It's 44 days
Step-by-step explanation:
Answered by
0
The wall will be built in 47 days or 46 days with some extra hours.
Number of days A takes to build the wall
Number of days B takes to build the wall
Number of days C takes to destroy the wall
According to the information given in the question,
let the time taken to build the wall once will be x days.
A, B, and C are working alternatively till the wall is done once.
Hence the one unit of work can be done in 3 days as they are working alternatively, so,
one day's work done by all three will be .
Therefore the work will be completed in .
Or we can say the wall will be built in 47 days or 46 days with some extra hours.
#SPJ2
Similar questions