4. A can do a piece of work in 20 days while B can do it in 15 days. With the help of C, they finish
the work in 5 days. In what time would C alone do it?
5. A can do a piece of work in 12 days and B alone can do it in 16 days. They worked together on i
for 3 days and then A left. How long did B take to finish the remaining work?
Answers
Step-by-step explanation:
For Question 4 :-
A do it in 20 days. that means in one day it will do in - 1/20 days.
Similarly for B is 1 / 15 for one day work.
Total Work with C is 5 days. ( For one day it is 1/5 )
So Work done by C is
A + B + C = 1 / 5
C = 1 / 5 - ( 1 / 15 + 1/ 20 ) = 1 / 12.
So C will Finish it in 12 days.
---------x-----------x------------x------------x---------x---------
For Question 5.
A do it in 12 days.
B do it in 16 days.
Total Work is done in 48 days.
Efficiency of A is 48 / 12 = 4
Efficiency of B is 48 / 16 = 3.
So In total work is done by a and b in one day
4 + 3 ---------48 days.
7 ---------------48. days.
Here they initially work both for 3 days ie
7 * 3 = 21 days. they work both but After it B left that means Remaining Work is ( 48 - 21 = 27 ) days which will be done by B.
and we know that time = work / Efficiency
days = 27 / 3 = 9 days Ans