Math, asked by samuelanitha1363, 11 months ago

4. ‘A’ can do a piece of work in 6 days and 'B' can do the same work in 12 days. If both
of them work together, then they will finish the work in
days

Answers

Answered by sohamdas59
1

Answer:

Hey mate here is your ans........

Step-by-step explanation:

A can complete a work in 6 days.....

In a day A complete 1/6 of work..

B can complete a work in 12 days....

In a day B complete 1/12of work...........

If they work together in a day,then they can complete (1/6+1/12)=3/12=1/4.......

Therefore,they can complete the work in 1÷1/4=4days...

Mark me as a brain list.....