Math, asked by shamapathan7860, 20 hours ago

4. A contractor employed 30 men to complete
he has to complete the work in 15 days,
employ?
(A) 50
(B) 40
(C) 30
(D)​

Answers

Answered by Anonymous
2

Answer:

The work requires 30 men x 20 days = 600 man-days.

In order to complete the same work in 15 days he needs 600 man-days/15 days = 40 men.

Since he already has 30 men he should engage 10 extra men to complete the work on time.

Answered by gopalpvr
1

Step-by-step explanation:

write the question clearly and correctly

you did not mension 30 men complete the work in how many days??

Similar questions