4. A contractor undertakes to dig a canal,
6 kilometre long, in 35 days and employed
90 men. He finds that after 20 days only 2 km
of canal have been dug. How many more men
must he employ to finish the work in time?(arrow method)
Answers
Answered by
5
Answer:
ANSWER
Total time given =35 days.
To dig a canal of 2 km in 20 days, 90 men were required.
So, to dig a canal of 1 km in 1 day,
2
90×20
men will be required.
So, to dig a canal of 4 km in 15 days
15
900×4
=240 men will be required.
As 90 men were already employed, so 150 more men are required.
Similar questions
English,
2 months ago
Math,
2 months ago
Computer Science,
4 months ago
Science,
4 months ago
English,
10 months ago
Computer Science,
10 months ago