4. A man can do a job in 15 days. His
father takes 20 days and his son
finishes it in 25 days. How long will
they take to complete the job if they
all work together? *
O 3.4 days
O 5 days
0 3.8 days
0 6.4 days
Answers
Answered by
2
Answer:
0 6.4 days is the correct answer.
HOPE IT HELPS YOU.
MARK ME AS THE BRAINLIEST.
Answered by
0
Answer:
bwnjeheekrjjrk
Step-by-step explanation:
6.4 is the correct answer