4 boys and 8 girls completed 1/3rd of work in 5 days. After that 3 boys and 3 girls increased and they completed 1/3rd more work more work in 3 days. If remaining work is completed in 2 days, then how many more girls should be increased.
solve the above question
Answers
Answered by
1
Answer:
13 girls will be there
Step-by-step explanation:
there are 8 girls and then tere are 3 girls increased in 3 days.so there is 1 girl increased in 1 day.In 2 days 2 girls will increase so 8+3+2=13 girls.
Answered by
0
Answer:
30 girls
Step-by-step explanation:
Total work done by 4 boys and 8 girls
4x+8y=1/15 (i)
Total work done by 7 boys and 11 girls
7x+11y=1/9 (ii)
Total work done by 7 boys and (11+a) girls
7x+(11+a)y=1/6 (iii)
solving eq (i) and(ii) we get
x=7/540 y=1/540
substitute x,y values in eq (iii)
we get a=30