E and F can complete a job in 12 days. F and G can
complete it in 15 days. E and G can complete it in
20 days. Find the time taken by E to complete it in
days).
(1) 24 (2) 36 (3) 30 (4) 45​

Answers

Answered by itzJitesh
0

Answer:

E & F=5/18 in one day

in 3 day=5/6th of total work

remaining work=1/6

g complete 1 work=12 days

1/6 work=2 days

2 days

Answered by gunjan55455
0

Step-by-step explanation:

e and f can complete a waork in 12 days means 1/12

e and g can complete a work in 20 days means 1/20

f and g can complete a work in 15 days means 1/15 in one day

add= 1/12+1/15+1/20=12/60=1/5

E F G)s 1 day work= 1/2×1/5=1/10

E = 1/10-1/15=3-2/30=1/30=30 days e can complete it in 30 days