4.If 125 people can do a piece of work in 75 days, in how many days will 25 people do it?
Answers
Answered by
0
Answer:
15 days
Step-by-step explanation:
125 people can do a piece of work in 75 days
1 man can do a piece of work in 75/125 days
i.e. 3/5 days
25 people can do a piece of work in (3/5) ×25
= (3 × 5 ) days
=15 days
Answered by
0
since the work is completed in 75 days
in one day 1/75 work will be done
so in one day 125 people do 1/75 work
in one day one person can do 1/(75*125)
in one day 25 people can do 25/(75*125) =1/375
Hence, to finish the work (1/375)*(375 days) = 1
So in 375 days 25 people will complete the work.