4 labourers can dig 20 m in 6 days .what portion will 2 labourers dig in 1 day
Answers
Answered by
0
Answer:
1.67m
Step-by-step explanation:
labour) (days) (portion of hole dug)
4------6-------20
1------6--------20/4
1------1---------5/6
2------1--------5/6×2=5/3m=1.67m
Answered by
0
Answer:
let 2 labourers dig "x" m in 1 day .
Step-by-step explanation:
4 labourers dig in 1 day
= 20/6 = 10/3 m
1 labourer dig in 1 day
= 10/3/4 = 10/12 m
so 2 labourers dig in 1 day
= 2 × 10/12 = 10/6 = 5/3 m
= 1 2/3m = 1.67 m Answer