*4 मजूर एक काम 20 दिवसांत पूर्ण करतात तर तेच काम 5 मजूर किती दिवसांत पूर्ण करतील ?*
1️⃣ 10
2️⃣ 20
3️⃣ 16
4️⃣ 80
Answers
Given:
4 मजूर एक काम 20 दिवसांत पूर्ण करतात तर तेच काम 5 मजूर किती दिवसांत पूर्ण करतील?
If 4 workers complete a task in 20 days, how many days will 5 workers complete the same task?
To find:
How many days will 5 workers complete the same task?
Solution:
We have the Man-Days formula as:
Here we have,
M₁ = 4 workers
D₁ = 20 days
M₂ = 5 workers
D₂ = need to find?
On substituting the given values in the above Man-Days formula, we get
← option (3)
Thus, the 5 workers will complete the same task in → 16 days.
------------------------------------------------------------------------------------------