4 man and 6 women both complete an work in 8 days when 3 man and 7 women complete this work in 10 days how many days complete this work 10 womens
Answers
Answered by
0
heya
Let 1 man's 1 day work = x
and 1 woman's 1 days work = y.
Then, 4x + 6y = 1/8
and 3x+7y = 1/10
solving, we get y = 1/400 [means work done by a woman in 1 day]
10 women 1 day work = 10/400 = 1/40
10 women will finish the work in 40 days
hope this helps u
if it helps mark me as brainliest please
Let 1 man's 1 day work = x
and 1 woman's 1 days work = y.
Then, 4x + 6y = 1/8
and 3x+7y = 1/10
solving, we get y = 1/400 [means work done by a woman in 1 day]
10 women 1 day work = 10/400 = 1/40
10 women will finish the work in 40 days
hope this helps u
if it helps mark me as brainliest please
Answered by
0
A. 35
B. 40
C. 45
D. 50
Answer: Option B
Explanation:
Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.
Then, 4x + 6y = 1 and 3x + 7y = 1 .
8 10
Solving the two equations, we get: x = 11 , y = 1
400 400
1 woman's 1 day's work = 1 .
400
10 women's 1 day's work = 1 x 10 = 1 .
400 40
Hence, 10 women will complete the work in 40 days.