Math, asked by naikravi1992, 4 months ago

4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat-weavers in 8 days? ​

Answers

Answered by sachin3588
0

Answer:

8Mats

Step-by-step explanation:

Rate of weaving is One mat per day per weaver...

So, 8 weavers can weave 8Mats in 8 Days