4 men and 10 women were put on a work.they completed 1/3rd of the work in 4 days. after this 2 men and 2 women were increased. they completed 2/9 more of the work in 2 days. if the remaining work is to be completed in 3 days, then how many more women must be employed?
Answers
Solution:
Let total amount of work = x
→(4 Men + 10 Women )'s 4 day's work =
→ (4 Men + 10 Women )'s 1 day's work = ------(1)
Remaining work = x - =
Now, 2 Men and 2 Women were increased.
→(6 Men + 12 Women )'s 2 day's work =
→(6 Men + 12 Women )'s 1 day's work = ---------(2)
Now remaining work =
Solving (1) and (2)
3 ×Equation.(1) - 2 × Equation.(2) → 6 Women =
→ 1 Women =
1 women can complete x amount of work in 216 days.
putting value of (1 Women) in equation (2), we get
→6 Men =
→ 1 Men =
So, one man can complete x amount of work alone in 108 days.
Total work done =
Remaining work = x - =
6 Men + 12 Women = work
Let P number of Women's be increased to complete the work in 3 days.
(6 Men + 12 Women ) 1 day's work =
(6 Men + 12 Women ) 3 day's work=
Remaining work =
P women one day's work =
P women three day's work=
So, 8 women's should be increased to complete remaining work.