Math, asked by aromala005, 6 months ago

4 men and 5 women can finish a work in 5 days while 3 men and 4 women can finish the work in 7 days .find the time taken by one man alone and that taken by one woman alone to finish the work ? PLZ HELP

Answers

Answered by neetusingh7584
0

Step-by-step explanation:

24 men can complete a work in 16 days

1 man's 1 days' work

12 men's 1 day's work

18 women can complete the work in 32 days

1 woman's 1 days work

6 women's 1 day's work

(12 men's + 6 women's) 16 days' work

Remaining work

(12 men's + 6 women's) 2 days' work

Remaining work

work is done in 1 day by 1 man

work will be done in 2 days by men = 16 men

Answered by SwarnaShreeARS2007
3

Answer:

Please follow me

Step-by-step explanation:

Thank my answers

Similar questions