Math, asked by abhayyadav15, 1 year ago

4 men and 6 boys are finich the plese of 5 day while 3 men and 4 boy finsh in 7 days find finish take time 1 men alone and 1 boy alone

Answers

Answered by TooFree
29

4M + 6B = 5D ----------- [ 1 ]

3M + 4B = 7D----------- [ 2 ]


Since both the work is the same:

(4 x 5)M + (6 x 5)B = (3 x 7)M + (4 x 7)B

20M + 30B = 21M + 28B

2B = 1M


Find the number of days needed if the work is to be done by 1 boy:

4M + 6B = 5D

Sub 1M = 2B:

8B + 6B = 5D

14B = 5D

1B = 70D


Find the number of days needed if the work is to be done by 1 man:

4M + 6B = 5D

4M + 3M = 5D

7M = 5D

1M = 35D


Answer: 1 boy alone will need 70 days and 1 man alone will need 35 days.



ezigduzenli: answer is wrong
Anonymous: What Do Yo Mean By It @MohitVerma3
Anonymous: Ok Brother
TooFree: I found.my error. give me a while.. let me kook for an edit to correct it.
Anonymous: Ok Sir
TooFree: I have corrected my error. I hope it is correct now. @abhayyadav15
Answered by Anonymous
14
Hii Mate!!

Here Is Answer To Your Question

Hope It's Correct And Helpful

For Queries Comment

______________________
Regards Vishal__________(BhamBhamBhole)
#BeBrainly✌✌