4 men and 6 boys are finich the plese of 5 day while 3 men and 4 boy finsh in 7 days find finish take time 1 men alone and 1 boy alone
Answers
Answered by
29
4M + 6B = 5D ----------- [ 1 ]
3M + 4B = 7D----------- [ 2 ]
Since both the work is the same:
(4 x 5)M + (6 x 5)B = (3 x 7)M + (4 x 7)B
20M + 30B = 21M + 28B
2B = 1M
Find the number of days needed if the work is to be done by 1 boy:
4M + 6B = 5D
Sub 1M = 2B:
8B + 6B = 5D
14B = 5D
1B = 70D
Find the number of days needed if the work is to be done by 1 man:
4M + 6B = 5D
4M + 3M = 5D
7M = 5D
1M = 35D
Answer: 1 boy alone will need 70 days and 1 man alone will need 35 days.
ezigduzenli:
answer is wrong
Answered by
14
Hii Mate!!
Here Is Answer To Your Question
Hope It's Correct And Helpful
For Queries Comment
______________________
Regards Vishal__________(BhamBhamBhole)
#BeBrainly✌✌
Here Is Answer To Your Question
Hope It's Correct And Helpful
For Queries Comment
______________________
Regards Vishal__________(BhamBhamBhole)
#BeBrainly✌✌
Attachments:
![](https://hi-static.z-dn.net/files/d38/3c43fafba13c08da45717457dd28fe08.jpg)
Similar questions