4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days.find the time taken by 1 man alone and 1 boy alone
Answers
Answered by
2
Step-by-step explanation:
1man =11 days
1boy =15 days