Math, asked by sahillincoln4531, 1 year ago

4 men and 6 women complete a task in 24 days. If the women are at least half as efficient as the men, but not more efficient than the men, what is the range of the number of days for 6 women and 2 men to complete the same task?
30 to 33.6 days
32 to 35 days
33.6 to 35 days
30 to 35 days


Anonymous: ___k off

Answers

Answered by hero9934
0

23.....................

Answered by sharonr
15

The range of the number of days for 6 women and 2 men to complete the same task is 30 to 33.6 days

Solution:

Let "m" represent men

Let "w" represent women

4 men and 6 women complete a task in 24 days

Therefore,

In\ one\ day\ 4m + 6w = \frac{1}{24}\ of\ work

If a woman is half as efficient as man, then

2w = 1m

6w = 3m

Therefore,

4m + 3m = \frac{1}{24}\\\\7m = \frac{1}{24}\\\\m = \frac{1}{168}

Number of days for 6 women and 2 men to complete the same task is:

6w + 2m = 3m + 2m = 5m

5m = \frac{5}{168}

Thus, they will take : \frac{168}{5}\ days = 33.6\ days

Given that,

4m + 6w finish in 24 days

Thus,

4m + 6m finish in 24 days

10m\ finish\ \frac{1}{24}\ of\ work\ in\ a\ day

Therefore,

1m finish in \frac{1}{240} of work in a day

6w + 2m = 8m

8m will take 240/8 = 30 days to finish the work

So, the range is 30 to 33.6 days

Learn more about this topic

8 men and 4 women together can complete a piece of work in 6 days. work done by a man in one day is double the work done by a woman in one day. if 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed ?

https://brainly.in/question/2874867

7 men and 3 women complete the work together in 10 days. 8 men and 2 women complete the same work In 8 days. How much work can be done by 10 men in one day?

https://brainly.in/question/8889381

Similar questions