Math, asked by uditworld2747, 11 months ago

4 men and 7 women can do a piece of work in 8 days.In how many days will 5 men and 2 women finish the work if each woman takes twice the time taken by one man ?

Answers

Answered by aleenaarif006
0

Answer:

10 days

Step-by-step explanation:

question says that a woman takes twice the time taken by one man

so 4 men and 7 women = 4 + 7/2 men = 4 +3.5 = 7.5 men

5 men and 2 women = 5 +2/2 men = 5 + 1 = 6 men

7.5 men = 8 days

6 men = x

the given problem is in inverse variation

7.5 * 8 = 6x

60 = 6x

x = 10 days

Similar questions