4 men can complete a task in 48 hours and 4 boys in 40 hours l. How many hours would three boys and 1 man working together take to complete the same task?​

Answers

Answered by PrajjwalJauhari
0

Answer:

Given,

4men complete it in 48 hrs

therefore one man = 12 hrs

4 boys complete it in 40 hrs

one boy= 10 hrs

3boys and one man will complete it in

30 +12 =42 hrs