4 men can construct a road in 7 days . how many men should be needed to completethe work in 2days
Answers
Answered by
0
Answer:
14 men are needed to complete the work in 2 days
Step-by-step explanation:
Given that 4 men can construct road in 7 days
Amount work = 4 × 7 = 28 men days work
We need to complete in work in 2 days
Number of men needed to complete the same work in 2 days is calculated as
Number of men = 28/2 = 14 men
Answered by
0
Answer:
let the number be x
4 : 7 : : x : 2
7x = 4X2
7x = 8
x = 8/7