4 men can do a piece of work in 5 days in how many days will 6 men complete it?
Answers
Answered by
1
Answer:
This is the case of inverse proportion
so,4/5=6/y
4×5=6×y
20/6=y
10/3=y
10/3 into mixed fraction is 3⅓
so,they will complete the work in 3⅓ days