4 men can do a work in 10 days working 8 hours a day. In how many days can 10 men do the same work, working 8 hours a day?
Answers
answer is - 2 and half of day
Step-by-step explanation:
cause if 4 man complete the work in 10 days
alright
so if the workers are double than days are less
just like
4 workers= 10 days
8 workers = half of 10 ( 5 )
2more workers = half of 5
so, half of five is - 2.5 ok
or if we talk about days to then it is 2 and half day
alright baccho
so I hope this answer is helpful for you guys
so pls comment down alright
byy....
Answer:
10 men can do the same work in 4 days
Step-by-step explanation:
Explanation:
Given , 4 men can do a work in 10 days and working 8 hours a day .
and 10 men do the same work and working 8 hours a day .
Step1:
Total work done by the 4 men = 4 men× 10 days × 8 hrs
= 320
Now let x be the days of 10 men do the same work
Total work done by the 10 men = 10 men × x days × 8 hrs
= 80x
But according to the question work is done by 4 men and 10 men is same .
Therefore , work done by the 4 men = work done by the 10 men
⇒320 = 80x
⇒ x =
Final answer :
Hence , in 4 days can 10 men complete the same work .