4 men each working 6 hours per day can build a wall in 9 days. How long will 6 men each working 3 hours per day take to finish the same work?
Answers
Answered by
1
Answer:
MDH ⇒ M D H = Constant. ⇒d2=12 ⇒ d 2 = 12 . ∴ Six men each working 3 hourss per day can finish the job in 12 days
Answered by
1
12 days
Step-by-step explanation:
⇒MDH= Constant.
⇒d2=12.
∴ Six men each working 3 hours per day can finish the job in 12 days.