4 men or 6 women can do a work in 42 day . The number of days 12 men or 3 women would take to finish the work is
Answers
Answered by
8
Answer:
Step-by-step explanation:
first multiply both 4 men and 6 women
then, 12 men and 3 women
now,
24:42
36:x
now, cross multiply both of them
24x = 42 * 36
x = 42 * 36
------------
24
when you cancel all three you will be left out with
9 * 7 = 63
therefore, the number of days 12 men or 3 women would take to finish the work is 63 days.
Answered by
0
Answer:first multiply both 4 men and 6 women
then, 12 men and 3 women
now,
24:42
36:x
now, cross multiply both of them
24x = 42 * 36
x = 42 * 36
------------
24
when you cancel all three you will be left out with
9 * 7 = 63
therefore, the number of days 12 men or 3 women would take to finish the work is 63 days.