Math, asked by Onkarkharade, 3 months ago

4 men or 6 women can finish a work in 16 days. In how many days the
same work is completed by 2 men and 9 women?

(A) 12 days
(B) 10 days
(C) 9 days
(D) 8 days​

Answers

Answered by XxphoneixX
0

Answer:

correct answer is 12 days mark me as brainliest

Answered by amankumargiri020
1

Answer:

HOPE THIS ANSWERS WILL HELP YOU

Step-by-step explanation:

Step-by-step explanation:

Given:

Let 1 man can do (\frac{1}{x})(

x

1

) of work per day and 1 woman can do (\frac{1}{y} )(

y

1

) of work per day .

We know that 4 men or 6 women can finish a work in 16 days,

4\times (\frac{1}{x} )\times 16 = 14×(

x

1

)×16=1

⇒ x=64

6\times (\frac{1}{y} ) \times 16 =16×(

y

1

)×16=1

⇒ y = 96

Now, the work completed by 2 by men and 9 women,

[ (2\times (\frac{1}{64} ))+(9\times(\frac{1}{96} ))]\times z = 1[(2×(

64

1

))+(9×(

96

1

))]×z=1

⇒ [ \frac{1}{32} +\frac{3}{32}]\times z = 1[

32

1

+

32

3

]×z=1

⇒ [\frac{1+3}{32}]\times z = 1[

32

1+3

]×z=1

⇒ [\frac{4}{32}]\times z = 1[

32

4

]×z=1

⇒ [\frac{1}{8}]\times z = 1[

8

1

]×z=1

⇒ z = 8

Therefore 2 men and 9 women can do the same piece of work in 8 days

THANK YOU

FOLLOW

Similar questions