Math, asked by bhargavi1713, 16 days ago

4 men working 6 hrs a day can finish job in 4 days how many day will 6 men working 8 hours a day to take to finish work​

Answers

Answered by joshisrishti12
0

Answer:2 days

Step-by-step explanation:

1 case- 4 men, 6 hrs , 4 days

2 case- 6men, 8 hrs,  x days

Using the formula ,

M1*D1*H1*=M2*D2*H2

4*6*4=6*8*x

x= 2 days

Answered by skaxms
0

Step-by-step explanation:

Men : hours : days :: men : hours : days

4 : 6: 4 :: 6 : 8 : X

4 x 6 x 4 = 6 x 8 x X

96 = 48 x X

X = 96/48

X = 2

In 2 days will 6 men working 8 hours a day to take to finish work.