4 painters can paint a house in 6 days. how many days would 3 painter take the paint the same house? ​

Answers

Answered by iwilanju
9

Answer:

Answer = 8 Days

Step by Step Explanation

4 painters paint house- 6 days

1 painter will paint a house - 6×4days

3 painter will paint - 6×4/3 = 8 days