Math, asked by vaibhavrgatty, 2 months ago

4 persons could fit new windows in a house in 6 days.1 of the persons fell ill before the work started.How long would the job take now?How many persons would be needed to fit the windows in two days

Answers

Answered by rashi676
0

Answer:

This is my favourite type of questions!!

Here's the answer....

Step-by-step explanation:

Persons Days

4 6

4-1=3 x

This is a case of inverse proportions.

4×6 = 3×x

24/3 = x

8= x

x=8

Hope it helps