4. Question 5.
'A', 'B' and 'C' can complete a piece of work in 28 days, 32 days and 42 days respectively. 'D' is as efficient as 'A' and 'C' together. Only one person can do the work on any day, so they take daily turns to do the work or
the first day 'C' does the work, followed by 'D', 'A' and 'B' on subsequent days; repeating this until the work is completed. In how many days will the work be completed?
Pick ONE option
A) 24 2/3 days
B) 26 5112 days
C) 38 11/24 days
D) 27 178 days
Answers
Answered by
2
Answer:
a
Explanation:
24 2/3 days
this is the answer