Math, asked by priyanshusinghzzz88, 4 months ago


4. Three painters can complete
a painting job in 24 days.
If 12 more painters join
the team 9 days after the
work has begun, how many
days would be required to
complete the job?​

Answers

Answered by prasadanand76
0

\huge\sf{\orange{\underline{\blue{\underline{☆✬◦ ANSWER ◦✬☆}}}}}

96days

Step-by-step explanation:

1 painter can complete its job in = 24/3

=8

days required for 12 more painter = 12x8

96

96days

Answered by rk03568
0

Step-by-step explanation:

Step-by-step explanation:

1 painter can complete its job in = 24/3

=8

days required for 12 more painter = 12x8

96

96days