4. Three workers can do a job in 12 days. One of the workers works twice as fast as each of the
other two. How long would it take the faster worker to do the job alone?
Answers
Answered by
0
Is this like direct and inverse variation method
shahriaral:
direct
Answered by
0
Answer:
The Time taken by slower worker to complete the job alone is 24 days .
Step-by-step explanation:
Given as :
Three workers can do a job in 12 days
One of the workers works twice as fast as each of the other two
Let the time taken to work done by three worker alone = x , y , y
And The time taken by faster worker = x
The time taken by slower workers = y , y
So, According to question
+ + =
∵ one worker works twice as other two
∴ = ..........A
So + + =
Or, =
Or, =
Or, =
From eq A
=
i.e =
Or, =
So, Time taken by slower worker = x = 24 days
Hence, The Time taken by slower worker to complete the job alone is 24 days . Answer
Similar questions