4. Two motor cycle mechanics, Vinod and Preetam, working together, can overhaul a motor cycle in 3
days. Vinod working alone can do the job in 5 days. If Preetam works alone, how long will he take to
do the same job?
Answers
Answered by
2
Answer:
2 days it take for Preetam to complete the same job