4 women and 10 men can complete a project in 2 days. 2 women and 2 men can complete the same project in 6 days. How long would it take for 1 man alone to complete the project? Assume that the rates at which a man and a woman works are fixed. days
Answers
Answered by
3
Answer:
36 days
Step-by-step explanation:
Here there is an indirect variation,
Let's denote women as w and men as m.
(4w+10m)×2=(2w+2m)×6
=>8w+20m=12w+12m
=>8m=4w
=>w=2m
And another equation for question is,
(2w+2m)×6=m×x ( x is number of days)
(You can also take (4w+10m)×2=m×x)
=>(2×2m +2m)×6=m×x
=>6m×6=m×x
=>x=36 days