4 worker can make a wall in 10 days . how many more workers will be needed to make wall in 5 days
Answers
Answered by
1
Answer:
8 workers will be needed to make the wall in 5 days
Step-by-step explanation:
m1 = 4 workers
d1= 10 days
m2 = ?
d2 = 5
m1 * d1 = m2 * d2
4 * 10 = m2 * 5
40 = m2 * 5
m2 = 40 / 5 = 8