4 workers complete the job at equal rates. Due to a problem, two of the workers quit after working for only one day. The remaining two workers completed the job but required 4 more days than it was originally scheduled. How many days was the job scheduled for?
Answers
Answered by
1
Answer:
5days
Step-by-step explanation:
explanation in image
Attachments: