Math, asked by itishree20177, 11 months ago

40 man can finish a piece of work in 26 days how many men will be needed to finish it in 16 days ​

Answers

Answered by hamzasohail8083
2

26/40=0.65and 0.65*16=10.5

Answered by and0
19

Step-by-step explanation:

Man power×days = Man power× days

40×26=man power× 16

1040= man power×16

1040/16= man power

man power= 65

So,65 men's needed to finish the work in 16 days.