40 men are required to finish a work in 26 days. How many men will be needed to complete it in 16 days?
yuvaraj7:
26×40/16...ans..65..
Answers
Answered by
1
40 men are required to finish a work in 26 days
1 men to finish work=26×40
men required to complete it in 16 days=26×40/16=65
65 men is the answer
if u like my answer mark it as a brainlist
1 men to finish work=26×40
men required to complete it in 16 days=26×40/16=65
65 men is the answer
if u like my answer mark it as a brainlist
Answered by
1
no. of men = 26×40÷16
= 65
= 65